Evening time Noise Monitoring Results
Station M5, Chuk Lam Ming Tong(near entrance)
Date Start Time End Time  Weather Noise level (dB(A)) Major Construction Noise Source(s) Observed Other Noise Source(s) Observed Remarks Temp. (°C) Wind Speed (m/s) Noise Meter Model / ID Calibrator Model / ID
Leq L10 L90
11/06/2014-a 22:45 22:50 Fine 58 62 53 Works in tunnel Road traffic at San Wan Drive  According to contractor, general construction works was in process accordance to CNP. 28.1 <5 B&K 2238  S/N : 2684503 B&K 4231  S/N: 3004068
11/06/2014-b 22:50 22:55 Fine 63 64 52 28.1 <5 B&K 2238  S/N : 2684503 B&K 4231  S/N: 3004038
11/06/2014-c 22:55 23:00 Fine 54 56 53 28.1 <5 B&K 2238  S/N : 2684503 B&K 4231  S/N: 3004068
11-Jun-14 22:45 23:00 Fine 60 64 51 Works in tunnel Road traffic at San Wan Drive  According to contractor, general construction works was in process accordance to CNP. 28.1 <5 B&K 2238  S/N : 2684503 B&K 4231  S/N: 3004068
Min. 54
Max. 63